The full job: emergency water main repair under a concrete drive, start to finish.
Short videos
Same day, in the rain: crew on site to find the leak.
A fire line runs right next to the leak, so the last part goes by hand.
Walkthrough of the work area before cutting.

Day 1: crew and equipment staged in the rain, work area coned off.

Saw cut setup over the leak.

Water surfacing through the joints and into the storm drain.
The leak, up close.
Keeping the water moving to the drain while we work.
Cut concrete sections lifted out with the mini excavator.
Cut opening and debris haul-off.
Hand digging inside the cut opening.
Digging out under the cut concrete.

Excavating by hand to expose the leaking line.

Pump running to keep the excavation dry while the crew works.

The leaking line exposed for the repair.
Line exposed, pump keeping the hole dewatered.

Rebar tied at the crossings before the pour.

Rebar grid set around the drain inlet.

Both repair areas reinforced and ready for concrete.
The tied rebar mat, up close.
Rebar runs from the cut edge up to the drain inlet.
Form board set along the drain inlet.
Prepped and ready for the pour.
Pour day: placing and leveling the new concrete at the drain.
Finishing the edge along the expansion joint.
Hand troweling up to the drain inlet.
Bull floating the new slab.

Trimming back the redwood joint before the epoxy fill.
Done: pressure washed and cleaned up.

Job complete.
Updates
Nov 4, 2026
Job complete: redwood expansion joints trimmed back, joints and saw-cut cross cuts filled with an epoxy concrete finish, and the work area pressure washed and cleaned up.
Nov 3, 2026
Rebar set, tied and doweled into the existing concrete, forms set at the drain inlet, and the new concrete poured.
Oct 31, 2026
Concrete over the leak saw cut and removed; the cut area was opened up and debris hauled off.
Oct 31, 2026
Excavation under the cut concrete, by machine and by hand, to expose the leaking line for the repair.
Oct 31, 2026
Leaking line exposed. A pump keeps the excavation dewatered while the line is uncovered for the repair.
Oct 30, 2026
Emergency call received. Crew, concrete saw and mini excavator mobilized the same day in heavy rain.
Oct 30, 2026
Phase 1 started: work area coned off and concrete saw cutting set up over the leak.
The problem
Water was surfacing through the expansion joints of a concrete drive inside a multifamily community and running into the storm drain. The leak was on a private water line under the paving, and the longer it ran, the more it threatened the paving and the ground under it.
The challenge
The drive is the main access lane for residents, so the work had to stay contained and coned off. A separate fire line runs close to the domestic water line, so the excavation has to be done carefully around live utilities. The work started in steady rain.
Our approach
We mobilized crew and equipment the same day the call came in, set up traffic cones around the work area, and staged a walk-behind concrete saw and a mini excavator. The plan: saw cut the concrete over the leak, remove it, excavate to expose the line for the repair, then backfill, compact and pour the concrete back.
The result
With the leaking line exposed for the repair, the crew removed the damaged material, filled the voids where soil had washed out from under the drive with flowable fill, set rebar tied and doweled into the existing concrete, and poured a new 8-inch concrete slab. To finish, the redwood expansion joints were trimmed back, the joints and saw-cut cross cuts were filled with an epoxy concrete finish, and the work area was pressure washed and left clean.
Services on this job
Serving this job area from San Antonio, Texas.
Status shown is completed. Client names, addresses and specific figures are left out on purpose.