Project

Emergency water main repair under a concrete drive

A private water main failed under the concrete drive of a multifamily community, pushing water up through the joints and into the storm drain. Our crew mobilized the same day, in the rain, with a walk-behind concrete saw and a mini excavator to cut out the drive, expose the leak and restore the concrete.

CompletedMedical Center area, San Antonio

The full job: emergency water main repair under a concrete drive, start to finish.

Short videos

  • Same day, in the rain: crew on site to find the leak.

  • A fire line runs right next to the leak, so the last part goes by hand.

  • Walkthrough of the work area before cutting.

  • Mini excavator, walk-behind concrete saw and traffic cones staged in a wet concrete drive between townhome-style apartment buildings

    Day 1: crew and equipment staged in the rain, work area coned off.

  • Crew member positioning a walk-behind concrete saw over the leak area while water runs across the drive

    Saw cut setup over the leak.

  • Water from a broken underground water main bubbling up around a storm drain grate in a concrete drive

    Water surfacing through the joints and into the storm drain.

  • The leak, up close.

  • Keeping the water moving to the drain while we work.

  • Cut concrete sections lifted out with the mini excavator.

  • Cut opening and debris haul-off.

  • Hand digging inside the cut opening.

  • Digging out under the cut concrete.

  • Night view of an excavation in a concrete drive, a crew member in the hole digging by hand beside the saw-cut slab edge, spoil piled to the side

    Excavating by hand to expose the leaking line.

  • Night view of the open excavation in a concrete drive with a dewatering pump and hose, a mini excavator, a skid steer and a walk-behind concrete saw

    Pump running to keep the excavation dry while the crew works.

  • Crew member standing in the excavation under the saw-cut concrete edge, working on the exposed water line with a light

    The leaking line exposed for the repair.

  • Line exposed, pump keeping the hole dewatered.

  • Close-up of rebar tied at the crossings inside the cut-out concrete drive before the pour

    Rebar tied at the crossings before the pour.

  • Rebar grid set in the cut-out area next to the storm drain inlet

    Rebar grid set around the drain inlet.

  • Rebar placed in both cut-out sections on either side of the storm drain inlet

    Both repair areas reinforced and ready for concrete.

  • The tied rebar mat, up close.

  • Rebar runs from the cut edge up to the drain inlet.

  • Form board set along the drain inlet.

  • Prepped and ready for the pour.

  • Pour day: placing and leveling the new concrete at the drain.

  • Finishing the edge along the expansion joint.

  • Hand troweling up to the drain inlet.

  • Bull floating the new slab.

  • Trimming back the redwood expansion joint along the storm drain frame

    Trimming back the redwood joint before the epoxy fill.

  • Done: pressure washed and cleaned up.

  • Finished concrete drive around the storm drain inlet after pressure washing

    Job complete.

Updates

  1. Nov 4, 2026

    Job complete: redwood expansion joints trimmed back, joints and saw-cut cross cuts filled with an epoxy concrete finish, and the work area pressure washed and cleaned up.

  2. Nov 3, 2026

    Rebar set, tied and doweled into the existing concrete, forms set at the drain inlet, and the new concrete poured.

  3. Oct 31, 2026

    Concrete over the leak saw cut and removed; the cut area was opened up and debris hauled off.

  4. Oct 31, 2026

    Excavation under the cut concrete, by machine and by hand, to expose the leaking line for the repair.

  5. Oct 31, 2026

    Leaking line exposed. A pump keeps the excavation dewatered while the line is uncovered for the repair.

  6. Oct 30, 2026

    Emergency call received. Crew, concrete saw and mini excavator mobilized the same day in heavy rain.

  7. Oct 30, 2026

    Phase 1 started: work area coned off and concrete saw cutting set up over the leak.

The problem

Water was surfacing through the expansion joints of a concrete drive inside a multifamily community and running into the storm drain. The leak was on a private water line under the paving, and the longer it ran, the more it threatened the paving and the ground under it.

The challenge

The drive is the main access lane for residents, so the work had to stay contained and coned off. A separate fire line runs close to the domestic water line, so the excavation has to be done carefully around live utilities. The work started in steady rain.

Our approach

We mobilized crew and equipment the same day the call came in, set up traffic cones around the work area, and staged a walk-behind concrete saw and a mini excavator. The plan: saw cut the concrete over the leak, remove it, excavate to expose the line for the repair, then backfill, compact and pour the concrete back.

The result

With the leaking line exposed for the repair, the crew removed the damaged material, filled the voids where soil had washed out from under the drive with flowable fill, set rebar tied and doweled into the existing concrete, and poured a new 8-inch concrete slab. To finish, the redwood expansion joints were trimmed back, the joints and saw-cut cross cuts were filled with an epoxy concrete finish, and the work area was pressure washed and left clean.

Services on this job

Serving this job area from San Antonio, Texas.

Status shown is completed. Client names, addresses and specific figures are left out on purpose.

Have a similar project?

Open 24/7. Free, itemized quotes within 24 hours of the site walk.